The initial phase was to perform discovery activity, reviewing any existing project collateral and via ‘interviews’ with key SME’s, stakeholders and Exec’s. This allowed the identification of solution, resource and implementation gaps and prioritisation of these.
The plan for the workstream and key deliverables were agreed with the CFO and Programme Director, including the agreement of resource required to achieve the delivery required. Resource was then recruited and onboarded to support solution design, readiness and testing.
Key to the delivery was to ensure that the key part of the solution, the build of a sub-ledger to capture all the financial transactions from the platform was in scope for build and could be delivered pre-migration. That required management of both internal and external suppliers to determine the solution and deliver it in a 3-month timeframe. The platform supplier was particularly difficult to manage, with any scope changes, even when agreed, having unclear delivery timelines.
Once the solution was determined and being delivered the next key element was to rectify the lack of engagement from the finance team. A standard approach of identifying where change was occurring through as-is/ to-be process mapping, understanding end reporting requirements, operating model review and resistance mapping was utilised. The original target date for the migration meant that this activity had to be completed in under 3 months at a time when finance was engaged in year-end reporting and regulatory enquiries around reporting quality.
From that change impact assessment, a readiness and communications plan was developed, covering the documenting of standard operating procedures, development of training material, delivery of training, operating model for a ‘soft launch’, cutover plan and post-migration support model. These were agreed with the Finance team and were aligned with wider Programme plans.
Finance was an outlier in the overall Programme delivery due to the lack of engagement and was perceived as a blocker to the overall success of the first migration. The introduction of governance and structure to the workstream allowed it to be integrated back into wider plans and reporting to ExCo. I joined the programme leadership team, and this allowed me to continue to build the confidence in delivery.